OneTopanga News

Featured image for “Caltrans TCB Road Closure Update 5-21-24”
05/22/24

Caltrans TCB Road Closure Update 5-21-24

Bulldozers and excavators are pushing down landslide material to SR-27, where dirt, rocks and boulders are being moved away by loaders so the pile doesn’t grow too big and spill over into the environmentally sensitive Topanga Creek. Work is continuing…
Featured image for “Caltrans TCB Road Closure Update 5-14-24”
05/15/24

Caltrans TCB Road Closure Update 5-14-24

UPDATE 5/14: Topanga Canyon Landslide at Postmile 1.8 on SR-27 Caltrans is building an access road to the top scarp. Work began May 10 and it will take several days to complete. The road will zigzag left of the slide…
Featured image for “Caltrans TCB Closure Update 5-10-24”
05/11/24

Caltrans TCB Closure Update 5-10-24

UPDATE 5/10: Topanga Canyon Landslide at Postmile 1.8 on SR-27 Caltrans is replacing a dirt berm and silt fence that protects Topanga Creek with a rock fence due to concerns about dirt falling into the environmentally sensitive creek during slide…
Featured image for “Caltrans TCB Closure Update 5-3-24”
05/04/24

Caltrans TCB Closure Update 5-3-24

UPDATE 5/3: Topanga Canyon Landslide at Postmile 1.8 on SR-27 Caltrans’ Botanist team is surveying the Topanga Canyon slide area for Fountain Grass, a non-native invasive plant. It will even grow vigorously in the gaps between sections of concrete and…
Featured image for “Caltrans TCB Closure Update 4-30-24”
04/30/24

Caltrans TCB Closure Update 4-30-24

UPDATE 4/30: Topanga Canyon Landslide at Postmile 1.8 on SR-27 Caltrans has met with Los Angeles County Public Works Department and is starting three joint task forces: Geology report review, material haul route planning, and emergency traffic management groups. These…
Featured image for “Caltrans TCB Closure Update 4-26-24”
04/27/24

Caltrans TCB Closure Update 4-26-24

UPDATE 4/26: Topanga Canyon Landslide at Postmile 1.8 on SR-27 Our Geotechnical Services team is mapping the slide. A Geotechnical Report will take about 1.5 to 2 weeks to complete. Information from the mapping operations will be used to refine the…
Featured image for “Caltrans Gives Somber News Re: TCB”
04/24/24

Caltrans Gives Somber News Re: TCB

The Topanga Town Council’s April 17th meeting focused entirely on the Topanga Canyon Boulevard (TCB) road closure. A record number of people (over 385) came to hear why the canyon isn’t already opened and to share their feelings on the…
Featured image for “TCB Road Closure”
03/21/24

TCB Road Closure

Caltrans, State and Local Officials at TTC Meeting On March 20, at the Topanga Library, the Topanga Town Council held a public meeting in which almost 100 people shared their concerns with Caltrans and government representatives over Topanga Canyon Boulevard’s…